Works progressed well last week, with the ramp fully installed and the Hoggin pathway along the ponds successfully resurfaced.

  • PLEASE NOTE; (For those with dogs and small children) that although the ramp and pathway past the ponds is completed, the gateway has yet to be installed and there is clear access between the main road and the pathway.  The new gate will be installed by the end of the footpath works.
  • Works continue this week with continuing the pathway through to the Durslade allotment site.
  • The gateways in Abbey Ponds and the Durslade allotment site will be removed and replaced during the course of works, but please be aware that there will be a period of time with no gates.
  • The plan is for the Hoggin Pathway to be installed through the Durslade allotment site to begin next Monday (17th November), digging for the preparation of this has begun.
  • PLEASE NOTE; the dates/timescales provided are entirely weather dependent and may be subject to change.

Thank you for your continued patience and understanding while these works progress.